Start Date and the Completed date to be the same day cause an error

Reported by: Lisa Burke Owned by: dbmuqs
Priority: medium Milestone: Post-NPGS Prod'n
Component: Database, Custom Reports Version: 1.9.4 Server
Severity: Keywords: Start and Completed Dates
Cc: Database Engine: N/A
Operating System: N/A

Description

In the Pathology/GEO dataview: if the start date and the completed date are the same an error occurs that says "Completed date must be after the start date" - can the system allow for them to be the same date? I found this when I was entering a pathology record that started and was completed on the same day.

Change History (6)

comment:1 by Lisa Burke, 11 years ago

Summary: All for the Start Date and the Completed date to be the same day → Start Date and the Completed date to be the same day cause an error

comment:2 by Lisa Burke, 11 years ago

I mean the Inventory Quality Status dataview

comment:3 by Kurt Endress, 11 years ago

Component: Dataviews → Data Maintenance
Owner: changed from Kurt Endress to dbmuqs

This involves the inventory quality status data trigger. If the completed date is less than the started date it gives the error "Completed date must be after started date." I don't know why it would do this when they are equal.

comment:4 by dbmuqs, 10 years ago

Resolution: → fixed
Status: new → closed

comment:5 by dbmuqs, 10 years ago

Resolution: fixed
Status: closed → reopened

It appears the problem is in the data that came over from GC. Modifying old data or copying from old data in the CT can cause the problem. Re-opened ticket until data cleanup occurs. Trigger part is OK.

comment:6 by Lisa Burke, 6 years ago

Resolution: → fixed
Status: reopened → closed